Comments: Deye PV balcony power plant commissioning and HA integration

 

Questions / Comments to Deye PV balcony power plant commissioning and HA integration

(newest first)


✍anonym
2024-03-21 08:06
Hi, thanks for the article. Question: can I limit the export to grid to zero somehow?
✍Bernhard
comment date 21.03.2024 08:48
as far as i know, you can not limit this inverter. Other inverters, such as Hoymiles can: https://www.libe.net/hms
In addition, you would need a smart meter and some logic to react on the consumption and production for changing the limit.

created by Bernhard
✍anonym
comment date 21.03.2024 10:43
i see. where i live it’s illegal to export any excess to the grid so in my case it should be always set to zero, no matter what. need to google it then, maybe will find a solution.

created by anonym

✍Fuat
2023-08-23 11:05
hey, thanks for detailed summary. after some time, would you recommend this product to invest or would you invest in some other product?
✍Bernhard
comment date 23.08.2023 11:17
The inverter has been doing its job reliably for me for half a year. Yes, I can currently recommend the device: if the limitations mentioned do not pose a problem: above all: statistics only at 5-minute intervals.

created by Bernhard
✍Fuat
comment date 23.08.2023 12:55
✍Fuat
comment date 01.09.2023 14:16
I have purchased this one (https://songsolar.com/en/products/balkonkraftwerk-800-watt-800watt-solaranlage-song-solar-gtb-800) and it comes with Tuya supported wifi invertor and data is real time (almost). I was able to integrate this with localtuya.

created by Fuat